The U.S. Nuclear Regulatory Commission (NRC) has issued an exemption in response to an August 2, 2022 request from Holtec Decommissioning International, LLC (HDI) that would permit HDI to investigate and report to the NRC when the Oyster Creek Nuclear Generating Station does not receive notification of receipt of a shipment, or part of a shipment, of low-level radioactive waste within 90 days after transfer, instead of the 20-day investigation requirement currently delineated in the NRC's regulations.